Screen Reader Access
Main Theme
A
+
A
A
-
हिन्दी
Home
About Project
Salient Features
Layout Plan
Media
Photo Gallery
Video Gallery
Press Release
News & Events
Progress
Kiru Login
Project Policies
Important Circulars
List of Holidays
Timing Notification
Organisation Structure
Contact Us
Home Page
About Project
Salient Features
Layout Plan
Photo Gallery
Video Gallery
Press Release
News & Events
Progress
Kiru Login
Departmental Circulars
Important Circulars
List of Holidays
Timing Notification
Organisation Structure
Contact Us
Intranet
Webmail
Back To Main Website
Progress Photographs August 2023
Home
Kiru
PH Excavation in progress
Curing of DT Deck slab (EL 1430m)
Mucking from Draft tube gate shaft 4
Secondary Grouting of the Cable Tendons (25 m long) installed at EL 1512
Epoxy treatment of Fixed Length of Cable Tendon to be installed in Power Intake at EL 1509 m between Intake 3 & Intake 4
Water Pressure Test of the Redrilled holes at EL 1509 m in Power Intake area (3&4) for Installation of Cable tendons (120MT Capacity) is in progress
PH Cavern
DT Inlet Structure Concrete Lift completed upto EL 1429.4 m