Screen Reader Access
Main Theme
A
+
A
A
-
हिन्दी
Home
About Project
Salient Features
Layout Plan
Media
Photo Gallery
Video Gallery
Press Release
News & Events
Progress
Kiru Login
Project Policies
Important Circulars
List of Holidays
Timing Notification
Organisation Structure
Contact Us
Home Page
About Project
Salient Features
Layout Plan
Photo Gallery
Video Gallery
Press Release
News & Events
Progress
Kiru Login
Departmental Circulars
Important Circulars
List of Holidays
Timing Notification
Organisation Structure
Contact Us
Intranet
Webmail
Back To Main Website
Progress Photographs July 2023
Home
Kiru
Mucking from DT Gate Shaft#4
DT inlet Structure Lift completed upto EL +-1428.30 m
Excavation in Power Intake area is in progress
Drilling for Installation of PRH (6m long) & Rockbolts ( 32 mm dia, 9 m long) in Power Intake area between EL +- 1492 to EL +- 1502 is in progress
Breakthrough of PS#4 and PH
Reinforcement fixing for foundation of Tower crane at Dam top is in progress
PH Excavation
Draft tube Gate Shaft#4 Excavation
Arrangement for stressing of cable tendon installed between Intake 3 & Intake 4 at EL 1512 m is in progress
Tc excavation of Bus ducts and gate shart in progress
Excavation id PH cavern along with bus ducts in progress
Drilling for Installation of 32 mm dia, 9 m long rockbolts is in progress between Intake 3 & 4