Screen Reader Access
Main Theme
A
+
A
A
-
हिन्दी
Home
About Project
Salient Features
Layout Plan
Media
Photo Gallery
Video Gallery
Press Release
News & Events
Progress
Kiru Login
Project Policies
Important Circulars
List of Holidays
Timing Notification
Organisation Structure
Contact Us
Home Page
About Project
Salient Features
Layout Plan
Photo Gallery
Video Gallery
Press Release
News & Events
Progress
Kiru Login
Departmental Circulars
Important Circulars
List of Holidays
Timing Notification
Organisation Structure
Contact Us
Intranet
Webmail
Back To Main Website
Progress Photographs June 2023
Home
Kiru
TC
PH Cavern Excavation
Excavation of Top Hz part of Bus ducts from TC
Excavation of Bus ducts and fixing of stiffeners for gantry rail in PH
PS 2, Drilling in Progress at RD 38m, El. 1453.80m
PS 1 Mucking in progress at RD 59m, El. 1439.80m
PS 3, Mucking in Progress at RD 42m, EL. 1450.30m
Reinforcement fixed for A6 Gallery at EL1393 n S3 block
Power Intake area Drilling & Excavation is in progress
Concrete Pouring in S5 block (Ds) is in progress
Concrete pouring in S3 block is in progress
Cleaning prior to concreting in S5 block